The Courts at Lake Kennedy Community Park
Lake Kennedy is a major recreational facility in Cape Coral, Florida, developed as part of the city’s voter-approved $60 million Parks and Recreation General Obligation (GO) Bond from 2018.

Original Concept: ~$5 million
Final Cost: $12.37 million (over 148% of early estimates)
Timeline: Years behind schedule, opened August 2024
Result: Beautiful facility with 32 pickleball + 12 tennis courts — but a prime example of significant cost overruns on the 2018 Parks GO Bond.
Project Overview and Features
- Location: Lake Kennedy Community Park (46-acre park in central Cape Coral), near the Sun Splash Family Waterpark entrance.
- Scope: A state-of-the-art racquet sports complex featuring:
- 32 pickleball courts
- 12 tennis courts
- Pro shop, concession stand, dining/event facilities, lighting for night play, and covered seating
- Purpose: Address growing demand for recreational amenities amid city expansion. It evolved from an initial smaller concept (part of a broader Parks Master Plan) into a larger “world-class” facility capable of hosting tournaments.
- Operator/Management: Managed by Sports Facility Company; rebranded as “The Courts Cape Coral.” It has been popular, with thousands of memberships sold and hosting professional events like the Carvana PPA Tour.
Timeline
- Master Plan (2016): Initial estimates for Lake Kennedy improvements around $2.9–5 million.
- GO Bond Approval (2018): Voters approved $60M for parks projects.
- Design/Planning: Scope expanded based on community input, pickleball/tennis pros, and design team recommendations (added courts, lighting, etc.).
- Bidding/Contract: Originally planned in phases; combined into one. Contract awarded January 2023 to Charles Perry Partners, Inc. for ~$10.7M construction (+5% contingency, totaling ~$11.2M awarded).
- Groundbreaking: March 2023.
- Completion: August 2024 (opened to public August 28, 2024).
- Delays: Approximately 4 years behind original schedule.
Expenses and Cost Overruns
The project is a notable example of budget challenges in the GO Bond program.
- Original/Initial Estimates:
- Master Plan: ~$2.9M–$5M.
- Early post-bond concept: Around $7M.
- Phase I bid estimate: $8.7M (before combining phases).
- Final/Current Budget: $12,366,517 (as of early 2025 audit data).
- 148% increase over the ~$5M original estimate referenced in audits (or significant overrun from the $7M figure).
- Contract + contingency started at ~$11.2M; grew with change orders and adjustments.
- Key Drivers of Increased Costs (per audit and city statements):
- Scope expansions from community/design input (more courts, lighting, covered seating, tournament capability).
- COVID-era inflation, supply chain issues, and construction cost increases.
- Planning process issues: Did not fully follow industry best practices for cost estimating and scheduling, leading to avoidable change orders.
City Perspective: Officials noted the enhancements created a larger, higher-value facility beneficial for residents and economic impact (tournaments, events), despite higher costs. Funding came from the GO Bond; the city has stated other projects were adjusted (e.g., Lake Meade and Tropicana Parks de-scoped from GO Bond) but overall promises are being met with reserved funds.
Audit Findings (April 2025 City Auditor Report No. 25-01)
- Construction complied with laws, regulations, and contracts.
- Issues Identified:
- Planning phase: Lacked best practices → budget/schedule overruns.
- Close-out phase: Missing formal close-out meeting and lessons-learned report.
- Recommendations focused on improving project management for future capital projects to avoid repeats.
This project highlights broader GO Bond challenges with overruns affecting the $60M allocation. Official sources include the City Auditor’s report, capecoral.gov parks pages, and recent budget docs.